Takt planning in ship outfitting.

Takt planning comes from the factory and from building construction. In a ship it works on spaces instead of floors. Every cabin runs through the trades in a fixed sequence, at a set pace. This page explains flow, takt and pull in outfitting, and how Sightyard shows them.

Takt, flow and pull in plain words

  • Takt is the fixed pace at which work moves from one space to the next. Each trade gets the same time per space and then moves on.
  • Flow means every space runs through the same phase sequence, and the trades follow one another without gaps or jumps.
  • Pull means a trade starts only where the space is released for it. Work is not pushed into a space that is not ready.

Together they turn the outfitting from a list of dates into a moving line. Site management then steers the pace of the build, not the list.

Why cabins suit takt

A cabin area has many similar spaces, deck by deck and fire zone by fire zone. The same work packages repeat in a fixed order. In Sightyard’s Module Cabin that order has six phases:

  1. 1 Cabin structure
  2. 2 Wet unit
  3. 3 Installation
  4. 4 Outfitting
  5. 5 Furniture, finish
  6. 6 Functional test

Repetition and a fixed order are what takt needs. Every phase becomes a wagon of the same train.

Reading the cabin train

The cabin train shows the whole process. Six phases run as wagons. The gap between two wagons is how far the rear phase lags behind, in percentage points. The gates Pre, First and Final show how many cabins are signed.

A gap that grows is the first sign that a phase falls out of takt, long before a date is missed.

Functional test
FT57%
Furniture, finish
E59%
Outfitting
D63%
Installation
C71%
Wet unit
B78%
Cabin structure
A91%
2 pp
4 pp
8 pp
7 pp
13 pp
Gates
Final inspection46% of cabins signed
First inspection58% of cabins signed
Pre inspection66% of cabins signed
Cabin train. Schematic figures from the demo ship.

Baseline, forecast, actuals

Daily dates in takt, as planned. The baseline stays fixed, the forecast moves, actuals are measured. A reschedule comes with a preview and an audit trail, so the plan can change without losing the original.

Progress against plan, SPI, forecast finish and the S-curve are shown per selection: a deck, a fire zone, a trade.

Pull from what is released

Each trade pulls its lot from what is released for it. Blocked spaces and open punch come first. Readiness asks the question before work starts: is the zone ready? Material, access, predecessors.

Takt planning and the Last Planner System

The Last Planner System was developed by Glenn Ballard and Greg Howell at the Lean Construction Institute. It plans with the people who do the work: a master plan, phase pull planning, a look-ahead that removes constraints, weekly work plans, and the percent plan complete (PPC) that measures how much of the planned work was done.

Takt planning sets the pace. Last Planner secures the commitments behind it. On board both come down to one question: is this space ready for the next trade?